Exploring Multiple thinkproject Modules on the Süd Autobahn Infrastructure Upgrade


Kraj / Region Austria
Branża Infrastruktura

Project
In Carinthia, Austria the Süd Autobahn (A2) runs from Vienna to the Italy border. It is one of Austria’s longest motorways. ASFiNAG were tasked with the renovation of this valuable infrastructure, including updating the Klagenfurt north bypass; the Falkenberg, Lendorf and Ehrentalerberg tunnels, as well as two underpasses. Amongst the rejuvenation works carried out were new ventilation systems, video detection, emergency call systems, and well as lighting and radio facilities.

Impressively, A2 remained operational and open to the public during all works carried out, which were completed in 2018.

Challenges
For large projects such as the A2 tunnel chain, due to unforeseen issues on-site, it may be necessary to carry out additional works, which can become a significant cost factor. According to ÖNORM B2110, this work must be ordered or approved by the client. For this reason, a considerable amount of admin may arrive at the client in the course of a project.

Solutions
ASFINAG also used the versatility of the thinkproject platform for this project. A variety of thinkproject modules can be individually adapted and expanded upon at any time they are in use. Both plan management, defect management, construction project files, inventory documentation, additional cost claims, applications for a regional application and director reports are handled within this central platform.

Outcome
In this ASFINAG project, suppliers submitted their applications directly via the thinkproject Project platform. These are automatically forwarded from there to the respective administrator of ASFINAG. As soon as there is a positive decision about the application, the control reports for the supplier are released. The supplier informs about these reports when they had carried out the works. ASFINAG thus has a transparent and structured documentation of the decisions taken, the resulting and performed directing works and their costs.

Testimonial
"thinkproject provides an optimal way to unite the collaboration and information sharing between AG and a large number of ANs on one platform and to ensure clear documentation. "
- Project Manager, ASFINAG BMG

    Client
    ASFiNAG are a publicly owned company who are responsible for the planning, finances, building and maintenance of the Austrian autobahns.

    Facts & Figures
    - Approximately 80 million Euro construction volume
    - Complete completion April 2019
    - 21.3 km total length of the tunnels to be rehabilitated

    Zamów prezentację

    Ustawienia plików cookie


    Nasza strona internetowa wykorzystuje pliki cookie i inne technologie, aby poprawić jakość korzystania z naszej witryny i zrozumieć, w jaki sposób korzystają Państwo z naszej strony internetowej. Proszę kliknąć "akceptuj", aby kontynuować lub "odrzuć", aby wyłączyć niefunkcjonalne pliki cookie. Gdy pliki cookie są wyłączone, z przyczyn technicznych nie można zapewnić pełnej obsługi strony internetowej.

    Aby dowiedzieć się więcej na temat plików cookie, prosimy zapoznać się z naszą polityką prywatności.